For a factory, the question of power goes beyond “is there electricity yet?”. A business needs to know where the power comes from, how the capacity is calculated, how the medium-voltage system is organised and what the supply plan is when the factory increases its output.
This is one of the infrastructure items Dung Phong has planned for from the outset.
POWER SUPPLY DELIVERED IN PHASES
According to the project’s planning and appraisal dossiers, the calculated apparent power for the whole cluster is about 10,832.67 kVA. This demand is based on the loads of the industrial plots, service area, technical infrastructure, car parks, green space and public lighting.
In the initial phase, power is expected to come from the existing 35 kV grid on feeder 372 E10.1. The approval in principle of the power supply from the Cao Phong Area Power Company sets the planned connection point on line 371 TC Dung Phong, with a total capacity of no more than 2,000 kVA for this phase.
In later phases, the main supply is planned to connect from the Cao Phong 110 kV substation under the power development plan.
The point to note is that the power system is not sized to a fixed demand at the start: its supply follows a roadmap that keeps pace with the cluster’s development and use.
POWER READY FOR EVERY PLOT
According to the design dossier, Dung Phong plans 4 transformer substations serving the service areas and technical infrastructure, and 12 RMU cabinets ready for connection to the industrial and warehouse plots. The low-voltage substations for each industrial plot will be sized to the needs of each secondary investor.
A precision engineering plant, a food processing facility and an electronics line may use the same land area but have entirely different power needs. That is why each factory’s supply should be calculated from its actual production lines, equipment, number of shifts and expansion plans, rather than giving every plot the same allowance.
NOT JUST CAPACITY, BUT A STABLE DISTRIBUTION NETWORK
The appraisal dossier proposes a medium-voltage ring network to improve the reliability of supply to the cluster. The medium-voltage lines use 35 kV, and underground cabling is being studied for integrated infrastructure, electrical safety and the landscape.
This matters to manufacturers because the cost of a power cut is not just the energy lost. It can also mean stopped lines, rejects, time to restart equipment and late deliveries.
So when considering an investment in Dung Phong, businesses should talk to the developer early about their expected capacity, peak load, voltage requirements and plans for increasing capacity, so that the connection can be planned from the preparation stage.
The power supply works on 3 October are one step in completing the technical infrastructure of Dung Phong Industrial Cluster, preparing the conditions businesses need to build and run their factories on the project’s schedule.
Contact
JADE – GENTLE – BUILD JOINT STOCK COMPANY
Address: 82 Chua Ha Street, Cau Giay, Hanoi
Hotline: 0981 702 005
Website: jadegentlebuild.com